14 de Julho Power Plant
Plant Location
Right Border - Cotiporã and Veranópolis
Left Border - Bento Gonçalves
Operation start date
Generator Unit 01 - 12/25/2008
Generator Unit 02 - 03/12/2009
Plant Location
Right Border - Cotiporã and Veranópolis
Left Border - Bento Gonçalves
Operation start date
Generator Unit 01 - 12/25/2008
Generator Unit 02 - 03/12/2009
Power station
Dam Gates
| Ficha técnica | |
|---|---|
| Installed Capacity: | 100 MW |
| Guaranteed Energy: | 50 MW average |
| Number of Units: | 2 |
| Type of Turbine: | Kaplan |
| Nominal Power: | 51,80 MW |
| Type of Dam: | Gravity, in Roller Compact Concrete |
| Reservoir Area: | 6 km² |
| Project Drop: | 33,50 m |
| > Click here to download the complete fact sheet | |
| Potência instalada | |
|---|---|
| Jan/09 to Dec/09 | 412.077 |
| 25 to 31/Dec/09 | 3.371 |